
CONSTRUCTION PROGRESS UPDATE
September 2026
PROGRESS AT AGLANCE
Key Metrics — July 2026
5.17%
OVERALL COMPLETION
98%
PILINGS WORKS
100%
BULK EXCAVATION
100%
PILINGS WORKS
75%
BLINDING CONCRETE (PCC)
0
SAFETY INCIDENTS(YTD)
WORK PACKAGE STATUS
Construction Progress Overview
STATUS
Enabling / Piling Works
Deep-foundation load-bearing capacity has been established across the entire building footprint, providing the structural base for all vertical construction.
Bulk Excavation to Formation
The site has been excavated to the design formation level across the full development
footprint, enabling systematic foundation construction.
Trim Excavation & Pile-Head Cutting
All zones have been prepared, and pile heads have been trimmed to specification,
ready for pile-cap and tie-beam construction.
Blinding Concrete (PCC)
Substructure
Pile Caps, Tie Beams, Waterproofing
PROGRESS


WORK PACKAGE
WORK PACKAGE STATUS
Construction Progress Overview

JUMEIRAH GARDEN CITY, DUBAI
DoubleTree by Hilton Residences
MONTHLY UPDATE
A Message from the Developer
Dear Valued Investor,
We are pleased to present the September 2026 construction progress update for DoubleTree by Hilton Residences, Jumeirah Garden City. This month marks a significant phase in the project’s development as we transition from enabling works into active substructure construction — a milestone that signals the beginning of the building’s physical form taking shape beneath the surface.
Since commencement, the project has advanced with precision and discipline. Piling works are substantially complete, bulk excavation has been finalised across the full development footprint, and our tower crane is now operational — preparing the site for vertical construction in the months ahead. We are proud to report zero recordable safety incidents since project inception, reflecting our unwavering commitment to international construction standards.
We thank you for your continued confidence in this landmark development and look forward to sharing further progress as DoubleTree by Hilton Residences rises in one of Dubai’s most prestigious emerging districts.
WORKS IN PROGRESS
Current Construction Activities
Current construction activities include pile cap concreting and tie beam reinforcement, with waterproofing and protection board installation continuing in the remaining foundation areas. Backfilling and compaction are progressing in preparation for ground slab works, alongside underground water tank wall reinforcement and column reinforcement. The foundation for Tower Crane 02 has been cast.
FROM THE SITE
Construction Photography — September 2026
Verified construction activity on site as of 30–31 July 2026.
THE VISION
Your Future Residence
DoubleTree by Hilton Residences represents a new standard of branded hospitality living in Dubai — from the arabesque-patterned podium façade to the resort-style rooftop amenities.

LOOKING AHEAD
What to Expect Next
In the coming months, the project will advance through the completion of blinding concrete across all remaining zones, followed by systematic pile-cap construction, tie-beam completion, and the commencement of raft foundation works. As the substructure phase concludes, the site will be prepared for superstructure construction — at which point the building will begin to rise above ground level.


CONNECT AND THRIVE

2801 Boulevard Plaza, Tower 1
Downtown Burj Khalifa District, Dubai, UAE
Phone: +971 4 448 8555
This document is issued by West F5 Development L.L.C for informational purposes only. Construction progress figures are based on verified site assessments as of the reporting cut-off date. Timelines and completion estimates are subject to change. All renders are for illustrative purposes and may differ from the final delivered product.













