CONSTRUCTION PROGRESS UPDATE
July 2026

Header copy.jpg

JUMEIRAH GARDEN CITY, DUBAI

DoubleTree by Hilton Residences

MONTHLY UPDATE

A Message from the Developer

Dear Valued Investor,
We are pleased to present the July 2026 construction progress update for DoubleTree by Hilton Residences, Jumeirah Garden City. This month marks a significant phase in the project's development as we transition from enabling works into active substructure construction — a milestone that signals the beginning of the building's physical form taking shape beneath the surface.


Since commencement, the project has advanced with precision and discipline. Piling works are substantially complete, bulk excavation has been finalised across the full development footprint, and our tower crane is now operational — preparing the site for vertical construction in the months ahead. We are proud to report zero recordable safety incidents since project inception, reflecting our unwavering commitment to international construction standards.


We thank you for your continued confidence in this landmark development and look forward to sharing further progress as DoubleTree by Hilton Residences rises in one of Dubai's most prestigious emerging districts.

PROGRESS AT AGLANCE

Key Metrics — July 2026

PROGRESS AT AGLANCE

Key Metrics — July 2026

5.17%

OVERALL COMPLETION

98%

PILINGS WORKS

100%

BULK EXCAVATION

100%

PILINGS WORKS

75%

BLINDING CONCRETE (PCC)

0

SAFETY INCIDENTS(YTD)

WORK PACKAGE STATUS

Construction Progress Overview 

STATUS

Enabling / Piling Works

Deep-foundation load-bearing capacity has been established across the entire building footprint, providing the structural base for all vertical construction.

Bulk Excavation to Formation

The site has been excavated to the design formation level across the full development
footprint, enabling systematic foundation construction.

Trim Excavation & Pile-Head Cutting

All zones have been prepared, and pile heads have been trimmed to specification,
ready for pile-cap and tie-beam construction.

Blinding Concrete (PCC)

Substructure

Pile Caps, Tie Beams, Waterproofing

PROGRESS

SUBSTANTIALLY COMPLETE
0.png
0.png

​WORK PACKAGE

COMPLETED
COMPLETED
IN PROGRESS
IN PROGRESS

WORK PACKAGE STATUS

Construction Progress Overview 

WORKS IN PROGRESS

Current Construction Activities

Current construction activities include blinding concrete works at 75% completion, pile-cap blockwork, shuttering and setting-out, tie-beam reinforcement, foundation preparation for waterproofing, and ongoing lift-pit reinforcement, dewatering, and site preparation for upcoming foundation works.

FROM THE SITE

Construction Photography - July 2026

Verified construction activity on site as of 30–31 July 2026.

THE VISION

Your Future Residence

DoubleTree by Hilton Residences represents a new standard of branded hospitality living in Dubai - from the arabesque-patterned podium
façade to the resort-style rooftop amenities.

LOOKING AHEAD

What to Expect Next

In the coming months, the project will advance through the completion of blinding concrete across all remaining zones, followed by systematic pile-cap construction, tie-beam completion, and the commencement of raft foundation works. As the substructure phase concludes, the site will be prepared for superstructure construction - at which point the building will begin to rise above ground level.

Green BG.jpg
White .jpg

CONNECT AND THRIVE

Select Project
West5 Logo-02.png

2801 Boulevard Plaza, Tower 1
Downtown Burj Khalifa District, Dubai, UAE
Phone: +971 4 448 8555

This document is issued by West F5 Development L.L.C for informational purposes only. Construction progress figures are based on verified site assessments as of the reporting cut-off date. Timelines and completion estimates are subject to change. All renders are for illustrative purposes and may differ from the final delivered product.